New synthetic athletics track at Sydney Academy of Sport

On this page

About the project

The NSW Government has committed $6.7 million for the development of a new synthetic athletics track at Sydney Academy of Sport, Narrabeen. The project will support users from grassroots to elite across a range of sports.

Scope

The project scope includes:  

  • A new World Athletics (WA) compliant synthetic athletics track with moisture resilient track surface  
  • New asphalt sub-base  
  • Drainage and stormwater system upgrades   
  • Accessibility improvements   

Fast facts

  • Address: 926 Wakehurst Parkway, Narrabeen NSW 2101
  • Forecast project completion: Mid quarter 4, 2026
  • Builder: CC Pines Pty Ltd (Head Contractor)
  • Consultants: SPORTENG (Principal Design Consultant)
  • Project Manager: NSW Public Works

Project update

The Office of Sport, and its appointed contractor have continued to progress construction of the replacement track throughout August with several project milestones achieved or well progressed, including: 

  • Remediation of the ground under the track well progressed
  • Geogrid, membrane and pavement foundation works advanced
  • Drainage infrastructure installation continued
  • Drainage works through the existing car park have been completed, enabling the temporary reopening of the car park
  • Track kerbing and footpath installation commenced
  • Asphalt planning and quality assurance activities progressed.

While recent wet weather and challenging ground conditions have impacted the programme and required additional remediation in some areas, mitigation measures are being implemented to support delivery of the project. 

Works remain active across the site, with preparations underway for asphalt installation and completion of the remaining track infrastructure.

Over the coming weeks, the contractor will complete the remaining ground improvement works, continue drainage and civil construction activities and prepare the site for installation of the track asphalt surface.

Project handover and completion remain forecast for mid-quarter 4 2026, subject to site and weather conditions. 

The Office of Sport will continue to work closely with the contractor to progress activities safely and efficiently with further updates to be provided as milestones are achieved.  

Updated: 1 September 2026

Forecast project timeline

July 2025:  

  • Delivery team established including appointment of NSW Public Works as project manager and SPORTENG as Principal Design Consultant.
  • Planning pathway determined.  
  • Preparation of Review of Environmental Factors (REF) commenced.  
  • Preliminary site investigations completed.

December 2025: 

  • REF approved.

December 2024:  

  • Concept design consultation.  

August 2025:  

  • Concept design finalisation.
  • Detailed design commenced. 

October 2025:  

  • Detailed design concluded.  

October 2025:  

  • Main works construction contractor procurement commenced. 

December 2025:

  • Main works construction contractor procurement concludes. 

January 2026:  

  • Site establishment and track installation construction commences. 

Late Quarter 3 2026:   

  • Operational readiness commences.

Mid Quarter 4 2026:   

  • Site works and track installation construction concludes. 
  • Project handover and completion.

Frequently asked questions

Visit our dedicated webpage for answers to frequently asked questions about the development of a new athletics track at Sydney Academy of Sport and Recreation.