New synthetic athletics track at Sydney Academy of Sport

On this page

About the project

The NSW Government has committed $6.7 million for the development of a new synthetic athletics track at Sydney Academy of Sport, Narrabeen. The project will support users from grassroots to elite across a range of sports.
 

Scope

The project scope includes:  

  • A new World Athletics (WA) compliant synthetic athletics track with moisture resilient track surface  
  • New asphalt sub-base  
  • Drainage and stormwater system upgrades   
  • Accessibility improvements   
Latest News
  • The main works construction tender assessment is complete with experienced head contractors CC Pines Pty. Ltd. appointed to lead the delivery of the project with the support of specialist synthetic sports surface consultants Polytan.
  • Onsite works are scheduled to begin in mid-January 2026, following confirmation of the contractor’s construction timeline.
  • Access to the existing track, infield and amenities (including the grandstand) will close from 5pm, Sunday 18 January 2026, and will remain unavailable until construction is complete. Any changes to this timeline will be communicated promptly to all stakeholders.

Updated – 23 December 2025

Fast facts

  • Address: 926 Wakehurst Parkway, Narrabeen NSW 2101
  • Forecast project completion: Quarter 3, 2026
  • Builder: CC Pines Pty Ltd (Head Contractor)
  • Consultants: SPORTENG (Principal Design Consultant)
  • Project Manager: NSW Public Works

Forecast project timeline

July 2025:  

  • Delivery team established including appointment of NSW Public Works as project manager and SPORTENG as Principal Design Consultant  
  • Planning pathway determined  
  • Preparation of Review of Environmental Factors (REF) commenced  
  • Preliminary site investigations completed 

December 2025: 

  • REF approved 

December 2024:  

  • Concept design consultation  

August 2025:  

  • Concept design finalisation  
  • Detailed design commenced  

October 2025:  

  • Detailed design concluded  

October 2025:  

  • Main works construction contractor procurement commenced   

December 2025:

  • Main works construction contractor procurement concludes 

January 2026:  

  • Site establishment and track installation construction commences 

Quarter 2 2026:  

  • Operational readiness commences  

Quarter 3 2026:  

  • Site works and track installation construction concludes
  • Project handover and completion 