Carss Park Pool

On this page

About the project

The Carss Park Pool Project will deliver a modern, outdoor, eight lane, 50 metre swimming pool with a swim wall, a 20 x 10 metre Learn to Swim pool and ancillary facilities that provide a safe, fit for purpose swimming facility for the local community.

The 50 metre pool will be designed within Swimming Australia’s ‘Local Level’ facility requirements.

Funding for the project is provided by the NSW Government , Georges River Council and the Commonwealth Government. 

Scope

The project scope includes:  

  • 50 metre x 8 lane (20m wide), heated outdoor swimming pool, with swim wall to allow the pool to be divided into two 25 metre pools.
  • 20 metre x 10 metre, shaded and heated outdoor Learn to Swim pool, with accessible ramped entry and swimming ledge.
  • Toilets, change rooms with lockers, family spaces and a shop/kiosk.
  • Shaded, spectator seating
  • Pool lighting
Latest News
  • Delivery of the Carss Park Pool project is progressing well, with key achievements to date including:
    • Planning approval obtained.
    • Facility Design complete.
    • ADCO Constructions appointed to construct the new facility.
    • Construction commencement on 10 August 2026.
  • Piling and inground works will commence September 2026.
  • The new Carss Park Pool is scheduled to open to the public in late 2027.

Read the latest media release and community notification (PDF, 334.12 KB) about the project.

Fast facts

  • Address: Carss Park, Carwar Avenue
  • Forecast project completion: late 2027
  • Builder: ADCO Constructions
  • Consultants: Tanner Kibble Denton (TKD) Architects
  • Project Manager: NSW Public Works
  • Project Leadership: Office of Sport on behalf of the NSW Government and Georges River Council

Forecast project timeline

January 2026:  

  • Documentation to support the preparation of development application (Review of Environmental Factors (REF)) developed

February 2026: 

  • REF development approval
     

October 2025:  

  • Detailed design commenced  

January 2026:  

  • Detailed design concludes
  • Additional site testing for structural design commenced (by Douglas Partners Engineers)

February 2026

  • Site testing concludes

July 2026:  

  • Construction contractor appointed.  

August 2026:  

  • Construction commenced.
  • Piling and inground works will commence September 2026.

Late 2027

  • Construction completion.

Late 2027:  

  • Operational testing and readiness activities
  • Pools open for public use.  

Enquiries

For more information, please contact the Office of Sport: 